Wednesday 23 October 2013

Bricks & plastering complete!

After yet another busy week at "The Palace", the brick work was finally completed on Tuesday (after a week's delay) and all the plasterboard has been fixed, stopped and sanded with the cornice fixed today!

Karlee & I are both over the moon with how the bricks look, especially against the darker coloured roof tiles and gutters and very happy that we went with the off-white mortar, rather than the standard "natural" (darker coloured) mortar. It will help to complement our garage door very nicely :) Externally there is not a whole heap left to do:

  • Fixing of eaves
  • External timber cedar cladding to front porch facade
  • Downpipes installed
  • In-fill above windows completed

Inside is coming together quite quickly as well with the next steps being:

  • Doors, architraves, skirting and cupboards
  • Waterproofing to wet areas (bathroom, powder room, ensuite and laundry)
  • Wall tiles to bathroom, powder room, ensuite & laundry

Once all the above internal & external items are completed, we will be on to our last stage. Whilst it does all seem to be coming together in a relatively timely manner, I did receive a text message from our Site Supervisor earlier this week regarding "very rough" estimated completion/handover date - and it's not before Christmas :(

Also, reality is starting to set in that lock-up is not far away and access will soon be quite limited. As someone that has enjoyed wandering in and out whenever I feel like it, it is going to be a hard reality to face when I'm left peering through windows to get a glimpse of any progress.

Latest photos are below.
Close up of bricks




Alfresco area

Garage

Theatre

Looking back towards front door

Kitchen / Dining

Kitchen

Dining & Living

Master bedroom

Kids TV Area





4 comments:

  1. I'm really enjoying following your blog. Your house looks lovely! We are also building with Plantation and will probably start around the time you are moving in. All the best for a smooth completion.

    ReplyDelete
    Replies
    1. Thanks for following. If you've got any questions, feel free to ask :) This is our first time building so happy to share any tips we've picked up along the way.

      Delete
  2. Hi I am at Tender stage with Plantation. I Was just wondering what bricks you chose? Are they Moon dust with raked mortar? They look amazing. How much was the upgrade for the off white mortar and raking?

    ReplyDelete
    Replies
    1. Hi - congratulations! Exciting times ahead! Your observation is 100% correct......Moon Dust with Off White Mortar (Raked). They came up an absolute treat! The upgrade for the mortar was approximately $1,600. The raking didn't cost anything - you can choose "ironed" or "raked" for the same cost. If you have any other questions, feel free to ask!

      Delete