Monday 27 January 2014

More flooring done & rangehood installed!

I was very happy to get a phone call yesterday from Harry, our flooring man, to let me know he was going to come and continue work at our place on Monday. After a solid 6 hours, we now have timber floors from the Entry through to the Living Area (excluding Kitchen). He is coming back tomorrow to finish the flooring and will then spend Wednesday finishing off the quadding around the skirts.

We also managed to install our rangehood today - which took much longer than anticipated as the installation measurements in the instruction manual were incorrect. But with some initial help from my Dad and some afternoon assistance from my father-in-law, the rangehood was conquered and it looks AMAZING!

I haven't managed to grout the Alfresco area as yet as the flooring man has been using it as his "prep" area - no hurry though - I will be endeavouring to finish next Sunday.

Tomorrow, the fun begins with the driveway being boxed up and poured and our TV Antenna is being installed.

The view from the Kitchen

Looking towards the front door

Hallway to Kids Retreat area

From the Front Door

Kitchen with the rangehood installed



Saturday 25 January 2014

We have keys!!!!!

After what has seemed like an eternity, we finally picked up our keys from Plantation on Thursday morning. The painter was on-site ready to make the final touch ups we identified, which disappointingly was ALOT!! However, I can't really blame Plantation too much given it was the Cleaners who were there that morning seemed to have made quite a mess of the skirtings and walls with their vacuum hoses.

Overall, the finish is great! There are still some "annoyances" however these have been duly noted on our Final Inspection Checklist (and maybe a follow up email or two to our Administrator to tack on a few more) and these will be rectified by Plantation over the course of the next 14 days.

The only "major" issues were:
  • Ensuite shower screen still not installed - happening Tuesday 28/1
  • Chip in kitchen cabinetry
  • Exterior painting very ordinary (seems to have been done in a huge rush on the day before handover)

We also had OptiComm (the Fibre Internet company) come visit on Thursday afternoon to run the fibre in to the home from the pit in the footpath. However we were quickly advised that it could not be connected as Plantation had not run the conduit to their connection point. After talking to Luke, it was revealed that OptiComm actually buggered up the pit installation and didn't run the connection point in to our boundary, hence Plantation couldn't connect to it. OptiComm now have to come out and rectify the error before they can connect the fibre to the home - a process that may take up to 28 days! Looks like I will have to be patient for our super-fast internet!!

Getting straight in to the swing of things on Friday, Dad & I completed the tiling of our Alfresco area, which has come up a treat!! It just needs to be grouted and the TermiMesh cut down - which we will be doing on Monday.

Whilst in the middle of tiling on Friday, I received a call from our timber flooring installer to advise that his job for Friday and Saturday had been cancelled so was available to start on our place earlier than expected. He came around briefly Friday afternoon to check the levels of our slab and was back again today to do the floor preparation (grinding of high points; filling of low points). Much to our surprise, when we returned this afternoon he had already started putting down the timber flooring and has so far completed the Theatre & Living Room. IT LOOKS AMAZING!!!!!!!!!!! We couldn't be happier with how all our colours have come together given we selected all of them from 5cm x 5cm samples!!

The best news is that our flooring man also mentioned he may look to come back Monday "if the weather is bad" - further questioning revealed he owns a boat so if the weather is bad, he won't be able to go out on the water. Here's hoping the weather is truly miserable!! Nonetheless, we are at least a day ahead on the flooring given he had to do some preparations that weren't budgeted or allowed for.

Other tid-bits happening next week:
  • Dad & I are installing our rangehood on Monday;
  • Our driveway is booked in for Tuesday morning, and we will be able to walk on by Wednesday afternoon;
  • Our TV Antenna installation is also booked in for Tuesday morning;
  • Our carpets are confirmed for Thursday;
  • Our gas-fitter & plumber is confirmed for Friday morning (gas cooker, dishwasher & BBQ)

And then the big day is Friday - when we start moving in to our home!!! By Saturday night, we will be going to bed in our very own "home sweet home" - CAN'T WAIT!!

A few photos below :)

Down the side of the Garage after the site clean up - much neater!

Pantry doors stained!!

Ensuite with mirror installed

Our front facade has been stained

So has our front door!

Alfresco area (before tiling)

Alfresco area (before tiling)

Alfresco area (before tiling)

Alfresco area (after tiling)

Alfresco area (after tiling)

Alfresco area (after tiling)

Timber flooring delivered

Living area with floors completed

Looking across the Dining Room - you can see they had to "fill" along the stacker doors

Our Theatre also has flooring!!

Another view of the Theatre (and our wheelie bins!)

Thursday 16 January 2014

HANDOVER DATE CONFIRMED!!!!!!

A very quick update to let everyone know that Plantation have confirmed our handover date for Thursday 23 January 2014 at 10am!!

We are now in a mad rush to get everything organised post-handover so that we can move in as quickly as possible, as we need to organise the installation of our timber floors, carpet and kitchen appliances as well as the laying of our driveway, the tiling of our alfresco area and the completion of our landscaping.

So far our flooring is booked for 28-30 Jan, the driveway 28-29 Jan and the kitchen appliances on 31 Jan - and provided everything goes as planned that week, we will be moving in on Saturday 1 February!!

From Plantation's side, there is not much left to do now:

  • Exterior painting / staining
  • Interior patch & paint
  • Staining of pantry & front doors
  • Ensuite mirror & shower screen
  • Plumbing fit off in main bathroom & powder room
  • Final house & site clean
Once we have had handover, I will post up some more photos :)

Thursday 9 January 2014

Back up and working in 2014

After what has seemed like an eternity, work has once again resumed at our house.

We have had a contractor working on our boundary retaining and fencing since Monday, which should be finished tomorrow. And this morning saw a little "hub" of activity from Plantation as our ceiling insulation was done and the fit off for our air conditioning nearly complete.

It is pleasing to see that Plantation have come back a couple of days early - hopefully this is the start of a final push to see us through to handover by 24 January.

A couple of photos below (even though I said no more until it was finished!).

Retaining & fencing down the right hand side of our house (looking from the street)

Fence posts in down the left hand side of our house (looking from the street)

Our ducted A/C unit!! Can't wait for air-con!!

Dodgy photo taken through window - our A/C ducts are in :)